BESS Logo
BESS.COM.UA Energy Systems
UA
Ukrainian Version (UA)

Engineering Department

sales@bess.com.ua
044 339-50-20
Microgrids for critical infrastructure of Ukraine | BESS.UA

Microgrids for critical
infrastructure of Ukraine

15.03.2026 14 min read Microgrid

Since October 2022, Ukraine has experienced an unprecedented series of attacks on energy infrastructure. Hospitals, water utilities, telecom towers and industrial facilities were without electricity for hours, and sometimes for days. A microgrid is not a luxury, but a necessity for any critical infrastructure facility.

99.99%
Microgrid uptime
20 ms
Switch time
72 hours
Autonomous work
60%
Reduction of energy costs

What is a microgrid?

A microgrid is a local energy system that can work as connected to the central network, and autonomous (island mode). Unlike a simple generator or UPS, a microgrid is an intelligent system of several energy sources and automatic control.

Microgrid components:

  • Generation: Solar panels (PV), wind generators, or micro-CHP
  • Accumulation: BESS (LiFePO4) is the heart of the system, providing instant switching and smoothing
  • Reserve: Diesel generator (for long outages when BESS+PV is not enough)
  • Management: EMS (Energy Management System) is the "brain" of the microgrid, makes decisions about flow distribution
  • Chain: Connection to the central network (grid) as the main or auxiliary source
☀ PV
EMS
BESS
⚡ Loading
Grid
|
Diesel

Why Ukraine needs microgrids NOW

Starting from October 2022 years, Russia is systematically attacking the Ukrainian energy infrastructure. Consequences for critical objects:

October-December 2022

The first wave of massive strikes. 40% of generating capacity was destroyed. Hospitals switch to diesel generators. Water channels are stopped for 6-12 hours.

Winter 2022-2023

Fan outages for 4-12 hours. Industrial enterprises lose up to 30% of productivity. Telecom operators are massively installing diesel generators on towers.

Autumn-winter 2023-2024

The second wave of attacks. Capacity deficit up to 6 GW. Blackout schedules are becoming the norm. The business buys generators en masse.

2024-2025

The attacks continue. The government announces a course for energy decentralization. Microgrids are recognized as a priority for critical infrastructure.

2025-2026

The first large-scale microgrid projects for hospitals and water utilities. BESS is becoming more affordable ($50-70/kWh at the cell level).

Key use cases

Hospitals and medical centers

Criticality: Patients' lives depend on electricity. Intensive care, operating rooms, ventilators cannot stop even for a second.
Solutions: 100 kW PV + 500 kWh BESS + 100 kVA diesel. Switching time: 20 ms (imperceptible to equipment). Autonomy: 72 hours.
Cost: ~$280,000. Payback Period: 4 years (tariff cost reduction + no downtime).

Water channels and pumping stations

Criticality: Stopping the water supply is a risk of contamination, a sanitary disaster. Sewage pumps cannot stop.
Solutions: 50 kW PV + 200 kWh BESS. The pumping equipment works autonomously for 8-12 hours. Diesel is connected automatically to continue.
Cost: ~$120,000. Savings on the tariff: $25,000/year.

Telecom towers and base stations

Criticality: Mobile communication is the basis of communication during martial law. Each tower serves thousands of subscribers.
Solutions: 5 kW PV + 30 kWh BESS (48V DC native). Completely replaces the diesel generator. Autonomy: 24+ hours.
Cost: ~$18,000. Fuel savings: $8,000/year. Payback Period: 2.5 years.

Military objects

Criticality: Headquarters, command posts, radar stations need uninterrupted power supply. Diesel is noisy and has a heat footprint.
Solutions: Mobile microgrid in a container: PV + BESS. Quiet operation, no heat trace. Compliance with NATO STANAG standards.
Advantages: Reduction of fuel logistics by 70%.

Grid-forming vs Grid-following inverters

This is the key technical difference that determines whether your microgrid will be able to operate autonomously:

  • Grid-following (GFL): The inverter "follows" the frequency and voltage of the network. When the network disappears, it turns off. Cannot run in island mode on its own. Most budget inverters are GFL.
  • Grid-forming (GFM): The inverter itself creates a reference frequency (50 Hz) and voltage (380V). Can work without an external network. Provides black start — starting the entire system of zero after a complete power outage. Mandatory for microgrids.

Attention: Not all BESS support island mode!

Most cheap systems use grid-following inverters. For a microgrid of critical infrastructure, be sure to request grid-forming inverter of certification on islanding. Manufacturers: SMA Sunny Island, Victron Quattro, Deye SUN-30K-SG04LP3, Sungrow SH-RT (HV series).

Comparison of solutions

ParameterNetwork onlyNetwork + dieselNetwork + BESSMicrogrid (PV+BESS+diesel)
Uptime92-95%99%99.9%99.99%
Switch time10-30 sec20 ms20 ms
Fuel costs$0$15-40K/yr$0$2-5K/year (min.)
Autonomy0While there is fuel4-12 hours72+ hours
ServiceMin.High (oil, filters)Minimallow
Noise / emissionsNoHighNoMinimal
CAPEX (500 kW)$0$50-80K$150-200K$250-350K
Black startNoyes (slow)Yes (GFM)Yes (instant)

Uptime by solution (%)

On the database for 2024, critical infrastructure of Ukraine

Network only
92-95%
Network + diesel
99%
Network + BESS
99.9%
Complete microgrid
99.99%

Cost of energy for 10 years ($/kWh)

TCO including CAPEX, fuel, maintenance, downtime losses

Network + diesel
$0.28-0.35
Network only*
$0.22-0.28*
Network + BESS
$0.14-0.18
Microgrid
$0.10-0.14

* Including cost of downtime and loss of production

Case: Hospital in Kharkiv region

Regional hospital with 400 beds. Critical equipment: resuscitation (50 kW), operating rooms (30 kW), laboratory (20 kW), oxygen concentrators (15 kW). Total critical load: 115 kW.

Solutions: 100 kW PV (rooftop) + 500 kWh BESS (LiFePO4, Deye) + existing 200 kVA diesel (as third level backup). Grid-forming inverter SMA Sunny Island.

  • Autonomy from BESS: 500 kWh / 115 kW = 4.3 hours (BESS only)
  • Autonomy of PV: In summer, PV covers 80% of the load, BESS discharges to 20% → autonomy 20+ hours
  • Autonomy is complete: With a diesel connection as an extension cord — 72+ hours
  • Project cost: $285,000 (after VAT and duty benefits)
  • Saving: $45,000/year (peak shaving + replacement of part of diesel fuel)
  • Payback Period: 4 years (taking into account grant co-financing — 2.5 years)

Stages of microgrid implementation

1. Energy audit (2-4 weeks)

Load analysis, identification of critical consumers, 24/7 consumption profile monitoring, insolation estimation for PV.

2. Design (4-8 weeks)

PV and BESS capacity calculation, equipment selection, power supply project, approval of OSR, RZA project.

3. Optional procedure (2-6 weeks)

Approval of Oblenergo, DSNS (fire safety), construction passport (for systems >30 kW).

4. Installation and commissioning (6-12 weeks)

Installation of PV, BESS, inverters, EMS. Setting up island mode. Switching testing.

5. Commissioning (1-2 weeks)

Final testing, staff training, act of technical readiness, connection of monitoring.

Frequently Asked Questions

How much does a microgrid cost for a small business?
A minimal microgrid (30 kW PV + 100 kWh BESS + grid-forming inverter) costs from $60,000-80,000. This provides autonomy of 3-6 hours for a load of 15-20 kW. For larger facilities (100+ kW) — from $200,000. The price depends on the required autonomy, power and availability of PV.
Is it possible to completely disconnect from the central network?
Technically, yes, if PV+BESS cover 100% of needs (taking seasonality into account). Practically, we do not recommend it. The grid remains the cheapest source of energy at night and in winter. An optimal microgrid uses the network as one of the sources, but can work without it.
What happens at night or on cloudy days without the network?
The BESS provides power for the estimated battery life (typically 4-12 hours). If the shutdown is prolonged and the BESS discharges to 10%, the diesel generator is automatically started. EMS optimizes the use of all sources for maximum autonomy.
Is a diesel generator needed in a microgrid?
For critical infrastructure, we recommend it as the "third level" of protection. For commercial facilities, autonomy of 4-8 hours is not necessary. For telecom towers, PV+BESS without diesel is usually enough. Diesel is insurance in case of a long outage (72+ hours) or prolonged overcast weather.
What is the minimum BESS power for island mode?
The minimum is your peak load power + 20% reserve. For example, if the critical load is 50 kW, the inverter must be ≥60 kW and the BESS must output ≥60 kW. The capacity depends on the required autonomy: for 4 hours — 200 kWh, for 8 hours — 400 kWh (taking into account DoD 90%).
Is there government funding for microgrids?
Yes. There are several programs: (1) IFC/EBRD credit lines through Ukrgasbank and Oschadbank at a preferential rate; (2) International technical assistance programs (USAID, GIZ) for critical infrastructure; (3) Exemption from VAT and import duties on equipment until 2027 years (~20% savings); (4) Separate grant programs for hospitals and water utilities.

Conclusions

A microgrid is not just a "generator + battery". It intelligent energy system, which provides uninterrupted power supply, reduces electricity costs and makes the facility independent of the state of the central network. For the critical infrastructure of Ukraine, this question is not "whether it is necessary", but "when to install it".

Microgrid project

Free energy audit and microgrid design for your facility.

Read also