BESS Logo
BESS.COM.UA Energy Systems
UA
Ukrainian Version (UA)

Engineering Department

sales@bess.com.ua
044 339-50-20
Hybrid: Sun + BESS + Diesel — How to save 70% of fuel | BESS.UA

Hybrid triad:
Sun + BESS + Diesel

15.06.2025 12 min read Microgrid
70%
Fuel economy
1.5-2.5
Years of payback
25+
Years of PV resource
$0.08
kWh hybrid

Ukrainian business massively purchased diesel generators in 2022-2023. Now he is massively horrified by the cost of a kilowatt ($0.8-$1.0). The Challenge & Problem Statement is not in the generator, but in how you use it. The integration of BESS and PV allows to reduce fuel consumption by 50-70% without replacing equipment.

Why "clean diesel" is a loss

A diesel generator (DSU) has a non-linear efficiency curve. It works economically only at a load of 70-90% of the nominal power. Below 30%, the "wet stacking" mode begins - incomplete combustion of fuel, formation of soot, accelerated wear of the cylinder-piston group.

The real situation: the office consumes 15-20 kW, but there is a 100 kW generator (because the start-up currents of air conditioners are "taken with a margin"). The result: the generator works at 20% power, burning 60-70% of the fuel from the maximum, and the efficiency drops from 35% to 15-18%.

The cost of kWh at different loads

100% (wholesale)
$0.30
70%
$0.40
40%
$0.65
20% (typical)
$0.95

Add to this: engine oil ($15-20/l, replacement every 250 engine hours), filters, turbine repair due to soot, depreciation of the diesel engine itself. The real cost of "diesel" kWh for a typical Ukrainian business is $0.80-$1.20 — 3-5 times more expensive than the network tariff.

Solutions: Cyclic work (Cycle Charging)

Add BESS (battery + hybrid inverter) to the system. The work algorithm changes radically:

  • Step 1: During a blackout, the facility is powered by BESS (silent, vibration-free, fuel-free).
  • Step 2: When the SOC drops to 20%, the EMS (Energy Management System) automatically starts the generator.
  • Step 3: The generator works at 80-100% power (maximum efficiency), simultaneously feeding the load and charging the batteries.
  • Step 4: After 1.5-2 hours, the batteries are charged to 95%. EMS shuts down the generator.
  • Step 5: The cycle repeats itself. The generator works 4-6 hours a day instead of 24.
"After installing BESS at 200 kWh, our 100 kW generator works for 3-4 hours instead of around the clock. Fuel costs dropped from UAH 120,000/month to UAH 35,000. Payback Period — 14 months." — Logistics center, Kharkiv region.

Scheme of energy flows of the hybrid system

PV panels
EMS controller
Load
.
BESS battery
EMS
.
Diesel (reserve)
EMS

Priority: Sun → Battery → Network → Diesel (last reserve)

Role of the Sun (PV): The third element of the triad

The addition of solar panels (PV-Diesel-BESS Hybrid) makes the system almost autonomous from April to September. The sun generates electricity during the day, the excess is stored in the BESS, and the generator becomes an emergency backup in case of prolonged cloud cover in winter.

Solar radiation in Ukraine varies from 1000 kWh/m2/year in the west (Lviv) to 1350 kWh/m2/year in the south (Odesa, Kherson). Even in Kyiv (1100 kWh/m2/year), 1 kW of PV generates 1100-1200 kWh per year, which makes solar generation economically attractive for hybrid systems.

PV generation by region (kW*h/kW/year)

Odesa
1 350
Dnipro
1 220
Kyiv
1 100
Lviv
1 000

Connection Architectures: AC vs DC Coupling

There are three main architectures for BESS of PV and generator integration:

AC Coupling

Principle: The PV inverter and the BESS inverter are connected in parallel to the 380V AC bus.

Pros: Simple installation, you can add BESS to the existing SES. The generator is connected directly.

Cons: Double conversion DC→AC→DC when charging the battery from PV (losses 5-8%).

When: Modernization of the existing facility with a generator.

DC Coupling

Principle: The PV array and the BESS are connected on a DC bus (48V or 400V+). One hybrid inverter.

Pros: Minimum losses (PV → BESS directly), one inverter, more compact.

Cons: Hybrid inverter required (Deye SUN-xK-SG04LP3), PV scaling limitations.

When: New projects "from scratch".

AC+DC Mixed

Principle: Part of PV on DC-bus (via hybrid inverter), part on AC (via grid-tie inverter).

Pros: Maximum flexibility, unlimited PV scalability.

Cons: More complex design and commissioning, more complex EMS is required.

When: Industrial facilities from 100 kW.

EMS Algorithm: The Brain of the System

The Energy Management System (EMS) is a controller that decides where to get energy and where to send it every millisecond. Modern EMS (Deye, Victron Cerbo GX, Schneider XW Pro) support programmable priorities:

  1. Priority 1 — Sun (PV): All generated energy goes to the load. Surplus - in the battery.
  2. Priority 2 — Battery (BESS): If PV is not enough (cloudy, night), power from BESS.
  3. Priority 3 — Network: If there is a network and the SOC of the battery is below the threshold — recharging of the network at the night rate.
  4. Priority 4 — Diesel: Start generator only when SOC < 20% and no other sources. Operation in Cycle Charging mode.

Advanced EMS also consider weather forecast (cloudiness), tariff zones (peak/off-peak), load schedule and battery health (SOH, temperature), optimizing system performance in real time.

Microgrid and island mode (Islanding)

The PV+BESS+Diesel hybrid system is essentially a microgrid — an autonomous energy system capable of working both in parallel with the external network and in complete isolation (island mode).

Key technology — grid-forming inverter (as opposed to grid-following). The grid-forming inverter itself sets a frequency of 50 Hz and a voltage of 380 V, creating a "virtual network" for other sources. Deye SUN-xK-SG04LP3 and Victron Quattro support this mode.

Black Start function — the ability to start from a complete power cut without an external network. The BESS supplies voltage to the grid-forming inverter, after which the generator (if required) and PV inverters can be started. Switching time: <20ms (seamless for IT equipment).

Real case: Production, Vinnytsia

Output data

  • Furniture production, shop 800 m2
  • Consumption: 80-120 kW (average 95 kW)
  • Generator: Cummins 200 kVA (worked 10-14 hours/day during outages)
  • Fuel consumption: ~80 l/day = ~4000 hryvnias/day

The system is installed

  • PV: 60 kW (120 panels on the roof of the workshop)
  • BESS: 200 kWh LiFePO4 (Deye + CATL)
  • Inverter: 3x Deye SUN-50K-SG04LP3 (150 kW)
  • EMS: Deye Cloud + PBX of programmable controller

Result

  • The generator works 2-3 hours/day instead of 10-14
  • Fuel consumption: ~15 l/day (81% reduction)
  • Savings: ~3,200 UAH/day = ~96,000 UAH/month
  • System CAPEX: ~$85,000
  • Payback Period: 22 months

Comparison of fuel costs (l/day)

100% Diesel
80 liters
PV + Diesel
40 liters
PV+BESS+Diesel
15 liters

Financial model: Payback Period according to scenarios

The payback period of the hybrid system depends on the duration of outages and the operating mode of the enterprise:

Parameter 8 hours/day 16 hours/day 24 hours (autonomous)
Fuel economy40-50%55-65%70-80%
Monthly savingsUAH 30,000UAH 65,000UAH 96,000
Payback Period3-4 years2-3 years1.5-2 years

Implementation Roadmap

Week 1-2: Energy audit

Installation of a network analyzer, measurement of the load profile 24/7, analysis of starting currents, the state of the TP and DGU.

Week 3-4: Design

Calculation of the optimal size of PV, BESS and EMS operation mode. Modeling in PVSyst/Homer Pro. Feasibility study of the financial model.

Week 5-8: Delivery

Direct import of equipment. Deye inverters — from a warehouse in Ukraine (2-3 days). CATL batteries - to order (4-6 weeks). PV panels — from the warehouse.

Week 9-11: Installation

Installation of PV array, installation of BESS racks, connection of inverters, integration of DSU through PBX. EMS commissioning.

Week 12: Commissioning

Testing of all modes (Grid-tied, Island, Black Start). Staff training. Connection to the monitoring system. Transfer of documentation.

Frequently Asked Questions

Can a BESS be added to an existing generator without PV?
Yes, and this is the fastest way to reduce fuel costs. BESS is connected in parallel through a hybrid inverter in AC Coupling mode. The generator works in Cycle Charging — only to recharge the batteries at maximum capacity. Fuel savings of 40-50% even without solar panels. PV can be added later.
What is the minimum BESS capacity for efficient operation?
The practical minimum is 2-4 hours of battery life under average load. For an office, 20 kW is 40-80 kWh. For the production of 100 kW — 200-400 kWh. A smaller capacity does not provide a sufficient "window" for an optimal generator cycle.
Does BESS affect generator warranty?
On the contrary, it is positive. The generator works for fewer hours and is always at optimal load (70-100%). This reduces wear, extends service intervals and prevents the "wet stacking" problem. Most manufacturers of diesel engines (Cummins, Perkins) confirm that Cycle Charging is the recommended mode.
What happens in a total blackout?
Grid-forming inverter (Deye SG04LP3) provides seamless switching in <20 ms — computers, servers and CNC machines do not notice the transition. The BESS feeds the load, the PV continues to operate (if it's daytime), and the generator starts automatically on command from the EMS when needed.
Are permits required to install a hybrid system?
A special license is not required for "behind-the-meter" systems up to 1 MW. Required: power supply project from a licensed designer, approval of local OSR (if the connection scheme changes), fire safety certificate for BESS in the premises. For PV on the roof, check the load-bearing capacity of the structure.

Already have a generator?

Find out how to reduce diesel costs by 3-5 times with the help of a hybrid scheme.

Read also