A grain store, livestock farm and cold warehouse need different backup systems. One must finish a drying cycle; another must keep ventilation or refrigeration running. Selecting storage from the site's total connection rating can leave some loads with unnecessary capacity and others with insufficient starting power.

Let the season determine the configuration

Prepare load profiles for the busy season and the rest of the year. Separate motors, compressors, controls and general services. Motors need starting data; controls need an acceptable interruption limit; refrigeration needs a restart sequence. Monthly consumption alone reveals none of these constraints. A large dryer that can pause safely should not automatically dictate the battery size for essential ventilation.

Solar helps when there is a surplus

Irrigation or cooling may already consume all daytime PV generation. In that case the battery has no free surplus to store: charging from the grid or a generator has a cost. Put generation and demand on the same time axis and identify actual charging windows. For seasonal operations, also establish what the BESS will do during the remaining months.

From specification to supply

Record dust exposure, temperature, location and service access in the enquiry. Grain dust requires a separate environmental assessment; an outdoor enclosure does not establish suitability for an explosive atmosphere. Ask USK Energy to compare packages by usable energy, PCS starting capability and warranty conditions for your operating duty.

Describe three working days instead of one agricultural site

Three profiles are useful for storage selection: the busiest seasonal day, an ordinary working day and a period of minimal activity. For a grain facility, these might represent receiving wet grain, handling stored stock and the off-season. For a livestock operation, they may involve different combinations of milking, ventilation, feed preparation and cooling. The distinction shows whether the battery is being purchased for a few critical weeks or will have a useful duty throughout the year.

Record more than total electricity consumption. Mark process starts and finishes, simultaneous motor starts and periods when an operator can defer a non-critical task. Two lines with the same installed power can require different backup arrangements because their operating sequences differ. If information is unavailable, prepare a measurement plan first. Adding nameplate kW values can produce an expensive specification without proving that the required process will remain available.

Define what preserving the process actually means

One area may need uninterrupted operation; another may need enough time to complete a stage safely. Controls and communications may require longer backup than the power equipment. Keeping a controller energised does not mean a conveyor or ventilation fan continues to perform its process function. Agree critical loads with the process specialist rather than selecting only the devices with the smallest electrical demand.

For cold storage, establish the product's permitted storage conditions and the compressor restart sequence. Do not replace these with an arbitrary acceptable pause. Livestock ventilation should be assessed under difficult weather conditions, not annual average temperature. For a dryer, distinguish the heat source, electric drives and control system. The battery supports the electrical part; it does not remove a shortage of another essential process input.

Give suppliers useful motor-starting information

List motor types, starting methods, variable-frequency drives, opportunities for sequential starting and available measurements. The PCS capability must be confirmed for the relevant load and duration, not reduced to the word overload. Check restart after an interruption separately: several devices returning together can create a different demand from an orderly start at the beginning of a shift.

LoadInformation needed beyond its kW rating
Conveyor or elevatorStarting method, mechanical load and permitted sequence
Refrigeration compressorRestart logic and product-cooling duty
VentilationMinimum required group and the most demanding weather conditions
Controls and communicationsPermitted interruption and required runtime
IrrigationOperating window, pump duty and scheduling flexibility

This information supports comparison of a BESS package and, where needed, separate online UPS units. The entire power load need not automatically pass through a UPS because a controller cannot tolerate interruption. Equally, a small controls UPS does not keep a motor running. Defining each group's boundary makes the commercial offer easier to understand and gives a reason for every major equipment item.

Work through one shift's energy balance

Suppose a hypothetical critical group needs 35 kW for the first two hours of an outage. Once the process is completed, demand falls to 12 kW for another three hours. Delivered energy is 35 × 2 + 12 × 3 = 106 kWh. Reserving 35 kW for all five hours would instead give 175 kWh. The difference is not a consequence-free saving: load reduction is valid only after the agreed process stage has finished.

Convert delivered energy into a battery configuration using the relevant losses, operating SOC window and resource allowance. Then examine the next day. If the short period of restored grid supply cannot replenish the energy used, the site needs another schedule, another source or a revised backup duration. More battery capacity merely postpones the difficulty when the daily energy balance remains negative.

Also consider what happens when the outage begins at an inconvenient time. A calculation starting from a fully charged battery at the beginning of a shift may not represent the point of highest production demand. State the minimum available reserve at that point. If the battery also performs tariff optimisation, its control rules must preserve the amount needed for the protected process.

Solar surplus must exist at the right time

Compare generation and consumption over matching intervals. A large monthly solar yield does not prove that energy is available for charging during the peak cooling or irrigation season. If daytime demand already consumes all generation, the battery will need another charging source. Do not count the same kWh both as direct solar self-consumption and as energy stored in the BESS.

Request two operating cases: a favourable sunny day and a working day with low generation. This separates economic use from the required backup reserve. Where protecting products is the main purpose, define the retained emergency energy before tariff optimisation. The business should understand how much remains available for other tasks after that decision.

Specify environment and off-season conditions

Describe dust, humidity, possible corrosive contaminants, temperature and proximity to process areas. An enclosure's ingress-protection rating does not establish suitability for an explosive atmosphere. Such locations require a separate assessment and suitable equipment; an ordinary outdoor cabinet should not be assumed appropriate. Ask for the manufacturer's requirements for cleaning, access and operation of auxiliary systems.

For the off-season, clarify permitted SOC, battery supervision, storage conditions and periodic actions specified for the actual product. Do not transfer instructions from one battery technology to another. The supply package should include understandable manuals and support contacts. Before the busy season, the business needs a way to verify readiness rather than simply confirming that the cabinet's display is illuminated.

Send USK Energy the three operating profiles, protected processes and motor data. Ask for separate identification of uninterrupted controls support, the main energy reserve and expansion options. This anchors equipment selection to preserving a particular product or process instead of treating agriculture as a single standard load.

Your inputs

Energy capacity for your backup duration

Change the inputs and save the result to discuss the equipment package.

Energy delivered to the load—kWh
Calculated initial DC capacity—kWh

P × t / (SOC window × efficiency × retained fraction). Percentages are converted to fractions. Assumes constant load; add auxiliary demand to it. Check PCS power, starting currents, temperature and transfer time separately. This is an energy balance, not a product selection.

Before requesting a quotation

Mark questions for which you already have a confirmed answer. Save the list and send unresolved points to the supplier.

Before requesting a quotation
0 / 3
What must remain powered during an outage?

Start with the loads that cannot stop. A server, a conveyor controller and the conveyor motor have different requirements: continuous power, retained process state and starting current. A single site power figure cannot describe all three. Separate loads into those requiring uninterrupted supply, those tolerating a brief interruption and those that can be shed during an outage.

A UPS bridges the transition for critical loads; a BESS provides stored energy; a generator can extend backup during a long outage. Check the UPS input requirements against the backup source output. Include battery recharge power after supply returns: restoring backup capacity must not overload the source.

USK Energy / B2B

From calculation to equipment

Preparing an equipment purchase? Send the load, backup duration or specification. USK Energy will clarify the configuration, compatibility and delivery terms.