Law 3220-IX:
Complete legal guide for the business of BESS
The market of energy storage systems (Energy Storage) in Ukraine has officially left the "grey zone". Law No. 3220-IX created a new class of market participants — Energy storage facility operator. This article is a complete legal guide for business: from a simple backup to making money from ancillary services.
1. Who is OUSE?
Energy storage facility operator — is a legal entity that owns or operates an energy storage system and is registered in the register of the NCRECP. This is a fundamentally new status in Ukrainian energy law, which differs from generator, supplier and system operator.
The status of OZE allows:
- Buy electricity on RDN/VDR for BESS charging
- Sell electricity during periods of peak prices (arbitrage)
- Provide support services — FCR, aFRR, mFRR (frequency control)
- Participate in the balancing market (BR) as a provider of flexibility
2. Who needs a license?
This is the most common question among business owners. The answer depends on two factors: purpose of use and installed capacity.
| Usage scenario | Power | License of NKRECP | OUSE status | New technical specifications |
|---|---|---|---|---|
| Backup for the factory (without admission to the network) | Any | Not needed | No | No* |
| Peak Shaving (optimization of own consumption) | Any | Not needed | No | No* |
| Arbitration (buying/selling on RDN) | ≤ 150 kW | Not needed | Registration | It depends |
| Arbitration (buying/selling on RDN) | > 150 kW | Mandatory | Necessarily | Yes |
| Auxiliary services (FCR/aFRR) | > 150 kW | Mandatory | Necessarily | Yes |
| Balancing market (BR) | > 150 kW | Mandatory | Necessarily | Yes |
* If the BESS is installed on the object of the existing connection and does not increase the total permitted capacity.
Key takeaway:
For 90% of businesses installing BESS for own needs (backup, peak shaving, tariff optimization) — no licenses, no OUSE status is required. This equates to installing a generator or UPS. Bureaucracy is minimal.
3. Procedure for joining networks
If your goal is only backup power or peak shaving on an existing facility, the procedure is as simplified as possible. But if you want to sell services to the network, you need to go through the full cycle.
Scenario A: BESS for own use (no leave)
Designing
Technical project of taking into account the capacity of the facility and relay protection.
2-4 weeksApproval of OSR
Notification letter to Oblenergo about the installation of BESS. Approval of RZA settings.
2-3 weeksInstallation and commissioning
Installation of equipment, configuration of BMS and EMS, connection.
3-6 weeksCommissioning
Act of technical readiness. For objects >100 kW — technical review.
1-2 weeksScenario B: BESS for Market Participation (BESS)
Application for joining
Submitting an application to the National Security Agency for joining BESS as a new object or changing an existing one.
1-2 weeksTechnical conditions (TU)
OSR issues technical specifications for requirements for RZA, SCADA, meters, grounding.
30 working daysDesigning
Technical project according to TU. Coordination of OSR.
4-8 weeksConstruction and installation
Construction works, foundation, cabling, installation of equipment.
8-16 weeksLicense of NKRECP
Submission of an application with a package of documents: charter, financial statements, technical documentation.
30-60 daysRegistration of OUSE
Entering into the register of the NCREKP, obtaining a market participant ID, connecting to SCADA.
2-4 weeksUkrenergo certification
For DP: checking response time, power, telemetry. Trial activation.
4-6 weeksContract of OSP
Contract of Ukrenergo (OSP) on the provision of SE. Connection to the ENTSO-E platform.
2-4 weeks4. "Active consumer" status
Law 3220-IX introduced the concept "Active consumer" — an enterprise that not only consumes, but also accumulates and can sell excess electricity. It's a simplified alternative to a full EMS for medium-sized businesses.
Advantages
Net Billing: Sale of surpluses by the mechanism of self-production.
Fewer imbalances: BESS smooths the consumption profile.
Simplified reporting: There is no complete set of requirements for OZE.
PV + BESS: An ideal combination for the business of solar panels.
Limitation
Power: Sales are limited to the level of own consumption.
Not for SE: An active consumer cannot provide auxiliary services.
Sale price: Fixed formula, not market price of RDN.
Counters: A two-zone or interval meter is required.
5. Ancillary services market: How to earn on BESS
Ukrenergo actively purchases frequency regulation services. BESS is an ideal tool for this due to its instantaneous response (milliseconds vs seconds for gas turbines). In 2025, Ukrenergo held tenders for the first time FCR (Frequency Containment Reserve) of BESS participation.
RDN (Day Ahead Market)
Day-Ahead MarketBuy electricity at night for 1.5-2.5 UAH/kWh, sell during the day for 5-8 UAH/kWh. Spread 3-5 hryvnias/kWh at 1-2 cycles/day. OUSE status and license are required.
VDR (Intraday market)
Intraday MarketTrade one hour before delivery. The volatility is higher, the spread up to 8-10 hryvnias/kWh during peak hours. Requires automated trading and integration of ENTSO-E platform.
FCR (Primary Regulation)
Frequency ContainmentAutomatic response to frequency deviation (±200 mHz). Response time: ≤30 seconds. Pay for capacity (MW), not energy. The Ukrenergo contract is a stable income.
aFRR (Automatic Secondary)
Automatic Frequency RestorationCommand from Ukrenergo to increase/decrease capacity. Activation time: ≤5 minutes. Double payment: for readiness (capacity) + for activation (energy). The most profitable market for BESS.
Potential annual income of BESS 1 MW / 2 MWh
Estimate based on tariffs 2025. Income stacking is possible.
Requirements for BESS to participate in the SOE market
To become a provider of support services, you must fulfill a clear set of requirements:
- License of NKRECP for energy storage (for power >150 kW).
- OUSE status — registration in the register of market participants.
- Ukrenergo certification: checking response time (for FCR — ≤30s, for aFRR — ≤5 min), activation power, stability of operation during a 15-minute test.
- SCADA/Telemetry: a system of monitoring and data transmission in real time to the dispatch center of Ukrenergo.
- Contract of OSP (Transmission System Operator) to provide auxiliary services.
- Minimum power: 1 MW for FCR/aFRR (several objects can be aggregated through the Aggregator).
6. Tax incentives and benefits
The government introduced a number of fiscal incentives to accelerate the development of Energy Storage in Ukraine:
Exemption from VAT on imports
Equipment for storage systems (battery modules, inverters, BMS) is exempt from VAT upon import until 12/31/2027. The UKTZED code must correspond to the list of the CMU. Saving: ~20% of the equipment cost.
Accelerated depreciation
BESS belongs to the 4th group of OZ of minimum amortization period 5 years (instead of 15 for normal equipment). This significantly reduces the income tax base.
Duty exemption
There is a zero rate of import duty for RES equipment and storage devices. Valid until 31.12.2027. Applies to complete container BESS, modules, inverters.
"Green" bonds
The government has announced a program of "green" bonds to finance Energy Storage projects. Rate: UIRD -2-3%. Available through state banks (Ukrgasbank, Oschadbank).
7. Permissive procedure: land and construction
For containerized BESSs (which are the majority of industrial systems), the procedure is simplified:
- Container BESS up to 30 kW: Category CC1 is a declarative principle. It is enough to notify DABI.
- Container BESS 30-150 kW: Category CC2 is a simplified procedure. A construction passport is required.
- BESS >150 kW: Category CC3 — complete project documentation, expertise, construction permit.
- Earth: For BESS on its own territory (on the territory of the plant, shopping center, logistics center) - no additional lead is required. For standalone BESS on a separate site — changing the target designation to "energy".
Importantly:
Any BESS of lithium-ion batteries needs coordination of the State Emergency Situations (fire safety). For systems >500 kWh, we recommend ordering a fire safety declaration. More details - in our BESS fire safety articles.
8. Comparison of the EU: Where is Ukraine and where is it going
The legislative base of Ukraine is approaching European standards, but with some differences:
| Parameter | Ukraine | Germany | Poland |
|---|---|---|---|
| Licensing | From 150 kW | From 1 MW | From 50 kW |
| Double taxation | Partially resolved | It has been resolved | Challenge & Problem Statement remains |
| Market FCR | pilot | Mature | It is developing |
| Aggregators | The law has been adopted, by-laws are in the works | They are fully working | Pilot phase |
| Revenue stacking | Allowed (limited) | Completely allowed | Allowed |
| VAT on imports | 0% (until 2027) | Standard 19% | Standard 23% |
9. Road map of regulatory changes
Legislation continues to evolve. Here are the key regulatory developments expected:
Q2 2025: Aggregation rules
NKREKP will approve by-laws regarding aggregators. This will allow combining several small BESS (30-150 kW) into one virtual unit for participation in the SE market.
Q3 2025: SE Tariffs for BESS
Ukrenergo will publish the first results of competitive bidding of FCR/aFRR of BESS. This will form market benchmark prices.
Q4 2025: Double taxation
The draft law on elimination of double taxation of BESS (when charging + when discharging). Exemption from the "consumer" tariff is expected when charging for OUSE.
2026: Capacity Market
Launch of the capacity market (Capacity Market) according to the EU model. BESS will be able to receive long-term contracts (3-5 years) for the availability of capacity, even without activation.
2027: Full integration of ENTSO-E
Synchronization of the European network will create new opportunities for cross-border trade in energy and auxiliary services.
Frequently Asked Questions
I want to install a BESS 200kw for the plant just as a backup. Do I need a license?
How much does the license of the NKREC for energy storage cost?
What is BESS "double taxation" and how does it affect payback?
Can my BESS 500 kW participate in the FCR market?
What are the risks of investing in BESS from the point of view of changes in legislation?
Is BESS exempt from VAT on importation?
Conclusions of BESS Ukraine
Legislative field for Energy Storage in Ukraine established and business-friendly. If your goal is energy independence (backup, peak shaving), bureaucracy is minimal: approval of Oblenergo and installation. If the goal is to make money on the market (arbitration, DP), the procedure is more complicated, but transparent and implemented.
Ukraine has competitive advantage before the EU: zero duty and VAT on the import of equipment until 2027 years. This is a window of opportunity that reduces CAPEX by 20% and significantly improves ROI.
"Don't wait for perfect legislation - there is already enough. Only wait for your competitor to install BESS first." — BESS Ukraine team
Planning a BESS?
Our lawyers and engineers will help with registration, licensing and technical conditions. The first consultation is free.