Industrial energy. USK Energy.
USK ENERGY / BESS

10 kV distribution explained: RP, TP, KTP, off-circuit tap changers

What a 10 kV distribution point is, how a package substation differs from a built one, what an off-circuit tap changer does and where in the supply chain…

10 kV distribution explained: RP, TP, KTP, off-circuit tap changers

Ukrainian single-line diagrams and grid documents use a set of abbreviations that rarely appear together in English. This page walks the whole chain from the point of common coupling to the workshop board — and answers the question that decides half the budget: connect the storage at 400 V or at 10 kV?

Key parameters

Voltage classes
6, 10, 20, 35 kV
Typical substation
160–1600 kVA
Off-circuit range
±2×2.5 %
BESS tie-in
400 V or 10 kV

The abbreviations, in the order they appear in the diagram

RP (РП) — distribution point
A node that takes one or two incoming 10 kV feeders and splits them across several outgoing ones. No transformer inside: the voltage is the same on both sides. Written as РП-10 кВ in Ukrainian drawings; the nearest English term is a medium-voltage switching station.
TP (ТП) — transformer substation
Steps 10 kV down to 400 V. Holds the transformer, the MV switchgear and the LV distribution board. Written as ТП-10/0,4 кВ.
KTP (КТП) — package substation
The same substation, but assembled and type-tested in a factory and delivered as one block. The difference is construction, not function: a package substation is craned onto a prepared foundation in a day. Variants: КТПН outdoor, КТПБ in a concrete enclosure, КТПМ pole-mounted, КТПТО with a radial infeed and an enclosure, common on smaller rural sites.
ShchTP (ЩТП) — LV board of the substation
The 400 V distribution board inside the substation: incomer, bus coupler, metering, outgoing ways. This is where most storage systems below 1 MW are physically connected.
ZRU / VRU (ЗРУ / ВРУ)
Indoor and outdoor switchgear arrangements at 10 kV. Industrial sites are almost always indoor.
TSN (ТСН) — auxiliary transformer
A small transformer feeding the substation itself: lighting, cubicle heating, breaker motors, communications. It matters for storage because the BESS cooling and controllers also need an auxiliary supply, and it has to be designed in.

Off-circuit and on-load tap changers

Two ways to trim the voltage ratio, and the choice affects storage directly.

An off-circuit tap changer — ПБЗ in Ukrainian documents, ПБВ in Russian ones — is a winding selector that can only be moved with the transformer de-energised. The standard range is ±2×2.5 %: five positions at −5 %, −2.5 %, nominal, +2.5 % and +5 %. The position is chosen once at commissioning against the measured supply voltage and then left alone for years.

An on-load tap changer (OLTC, РПН) does the same job with a motor drive and an arc-quenching diverter, switching automatically without interrupting supply. Range is typically ±8×1.25 % or ±9×1.78 %.

Off-circuit and on-load tap changers
Off-circuit (ПБЗ)On-load (РПН)
Switchingde-energised onlyon load, automatic
Range±5 %, 5 positions±10–16 %, 17–19 positions
Transformer pricebaseline25–40 % higher
Maintenanceeffectively nonescheduled drive inspection
Typical usedistribution substations 10/0.4 kVmain step-down 35/10 kV

Why this matters for a BESS: the inverter has a narrow operating voltage window and trips out below roughly −10 % of nominal. On a site with an off-circuit changer and a chronically sagging supply, the tap position must be checked before installation — otherwise the system will trip and the fault will be looked for in the battery rather than in the substation.

Connect at 400 V or at 10 kV?

The fork that decides half the budget. The rule of thumb: below 1 MW, 400 V is usually cheaper; above 2 MW it is almost always 10 kV; in between, both are costed.

Connect at 400 V or at 10 kV?
400 V connection10 kV connection
Where physicallyspare way on the LV boarda cubicle in the RP or in the substation
Transformer needednoyes, a dedicated step-up for the BESS
Sensible power limitup to 1–1.5 MWfrom 1 MW upwards
Cable lossesnoticeable beyond 100 msmall, the route can be long
Added costlarge-section cable, sometimes an LV board rebuild transformer, MV cubicle, protection relays, design
Approval timeshorterlonger, technical conditions needed

The detail that is easy to miss: at 400 V the constraint is not the inverter but the cable cross-section and the rating of the incoming breaker. An 800 kW system draws around 1,200 A on the low side. That current means busbar or several parallel cables, and beyond a 60–80 m route the cost of copper starts to exceed the cost of a step-up transformer.

Second: a spare cubicle. If the distribution point has none, adding one — with protection and approvals — adds weeks to the programme and its own budget line. It is the first thing worth checking on your own site before requesting a quote.

What the grid side needs, in order

  1. An up-to-date single-line diagram. The most common delay at the start: the drawing exists but dates from 2011 and half the feeders on it are gone.
  2. Contracted capacity and the actual maximum over the last twelve months, from bills or the supplier's portal.
  3. A logged load profile from an analyser on the LV board — at least a week at 1–15 minute resolution. Without it, capacity is a guess.
  4. Confirmation of a spare cubicle or a spare way on the LV board, plus headroom on the incoming breaker.
  5. Notification or technical conditions from the DSO, depending on whether power will be exported.
  6. An updated electrical design: point of connection, protection, metering, earthing.

Items 1–4 can be done in-house within two weeks and determine 80 % of the system configuration. If you already have them, the questionnaire takes about ten minutes and comes back with a specific arrangement.

From the 10 kV network to the workshop

The same site on one diagram. In orange: the two points where storage is actually connected.

Left of the substation the voltage is 10 kV, right of it 400 V. A system up to 1–1.5 MW lands on a spare way of the LV board; anything larger takes its own cubicle in the distribution point through a dedicated step-up transformer. That choice drives most of the connection budget.

Frequently asked questions

What is an RP-10 kV?
A distribution point at 10 kV — a node that receives an incoming feeder and splits it into several outgoing ones without changing the voltage. There is no transformer inside; the transformer sits further along, in the substation.
What is the difference between a TP and a KTP?
The function is identical — stepping 10 kV down to 400 V. A KTP is a package substation, assembled and type-tested in a factory and craned onto a foundation in a day. A TP is built on site. Variants: КТПН outdoor, КТПБ concrete-enclosed, КТПМ pole-mounted, КТПТО with a radial infeed.
What does an off-circuit tap changer do?
It selects a winding tap to trim the transformer ratio, over a standard range of ±2×2.5 % in five positions. It can only be moved with the transformer de-energised, so the position is set once at commissioning. Written as ПБЗ in Ukrainian documents and ПБВ in Russian ones.
Should a battery system be connected at low or medium voltage?
Below 1–1.5 MW, a 400 V connection into a spare way on the LV board is usually cheaper. Above 2 MW, a dedicated step-up transformer at 10 kV is normal. In between, cost both: beyond a 60–80 m cable route the copper on the low side can cost more than the transformer.
What if the distribution point has no spare cubicle?
A new cubicle with protection and approvals can be added, but it adds several weeks and a separate budget line. Check this at the very start, together with the headroom on the incoming breaker.
Why does the tap position matter for a BESS?
The inverter has a narrow operating voltage window and trips below roughly −10 % of nominal. On a site with a chronically low supply voltage and an off-circuit tap changer, the tap must be checked before installation — otherwise the system trips and the cause is looked for in the battery instead of the substation.

Figures shown are indicative. We supply the equipment and size the system; design, installation and commissioning are arranged through contractors when needed and quoted separately. Exact sizing follows a load-profile analysis.

YOUR NEXT STEP

Need equipment?
Request a quotation.

Send a model, specification or describe your requirements. We will clarify the configuration, check supply terms and prepare a price quotation.

044 339-50-20sales@usk.ua09:00–18:00 · Kyiv

A phone number or email is enough to contact you.

USK ENERGY / BESS

What system does your business need?

USK ENERGY · AI

BESS and energy equipment assistant

Project brief ↗

Messages are sent to the AI service to answer and process your enquiry. Privacy