BESS.COM.UA
BESS.COM.UA Energy Systems
Industrial battery storage in Brovary · 50 kW – 5 MW

Industrial Battery Energy Storage for Brovary, Kyiv Oblast

Feasibility study for a battery energy storage system (BESS) in Brovary starts with numbers: your 0.4/10 kV load profile, your electricity tariff, and the grid constraints of DTEK Kyiv Regional Grids. Here's the pre-design checklist we run through before proposing a single battery.

Key parameters

Location
Brovary, Kyiv Oblast, Ukraine (50.5111, 30.79)
Grid operator
DTEK Kyiv Regional Grids
Typical industrial objects
Warehouse complexes, food production, steel structures, logistics
Contractor capability
50 kW to 5 MW, LiFePO4, liquid cooling, full EPC

1. What to measure on site

We record actual power demand at your transformer substation. For a warehouse complex, that means logging every 15 minutes for at least two weeks — ideally over a month — to catch peak events. Same for food production lines, where cooling and freezing cause sharp load steps.

For steel structures plants, we look at welding equipment and cranes: they create short, high-current spikes. Those peaks are what a BESS can shave, but the exact kW and duration matter. A 50 kW storage unit will not cover a 500 kW crane start.

2. Which documents to pull

Get your electricity supply contract, the latest invoice with the hourly tariff breakdown, and the technical conditions (TU) from DTEK Kyiv Regional Grids. The TU specify your permitted connection capacity and the voltage level — 0.4 kV or 10 kV. That determines the inverter topology and transformer needs.

Also request a single-line diagram of your internal network. If you operate a logistics hub with multiple buildings, we need to know where the storage can connect without overloading existing cables.

3. Grid constraints to verify with DTEK

DTEK Kyiv Regional Grids handles connection applications for industrial sites in Brovary. They will state whether your new storage can export to the grid or only operate behind the meter. Most industrial BESS in the region are installed behind the meter for peak shaving.

Ask DTEK about the allowed short-circuit power at your point of common coupling. At 0.4 kV, a large BESS may require a dedicated transformer; at 10 kV, the connection is simpler. We have seen both cases.

4. The solution: sizing, chemistry, and controls

Once we have the load profile and grid constraints, we size the BESS in kWh and kW. For a typical Brovary warehouse with a 200 kW peak and 20 minutes of duration, a 100 kW / 100 kWh system with LiFePO4 cells and liquid cooling fits. For food production with longer peaks, we step up to 500 kW / 1 MWh.

We use CATL or other Tier-1 LiFePO4 cells, IP55/C4 cabinets, and a BMS that talks to our EMS/SCADA. The control strategy is set to your tariff schedule: charge at night (if you have a two-zone tariff) and discharge during the morning and evening peaks. Payback is typically 5–7 years, but without an hourly load profile, that figure is rough.

5. What we deliver and what we do not

BESS Ukraine Engineering Group is a full-cycle EPC contractor: audit, design, supply, installation, commissioning, and service. We handle industrial storage from 50 kW to 5 MW, in 20/40 ft containers if needed. We provide the TU approval process support and guarantee the system meets DTEK's requirements.

We do not install residential systems — that is SolarProm.com.ua. And we will not promise a payback under 4 years if your tariff does not support it. Call us at +380 44 339-50-20 or email engineering@bess.com.ua for a site survey.

Frequently asked questions

How much does a BESS for a warehouse in Brovary cost?
Depends on the size and scope. A 100 kW / 100 kWh system with installation starts around 2.5 million UAH. We can give a precise quote after a site audit and load profile analysis.
Do I need DTEK approval to install a battery storage?
Yes, if you connect to the grid or modify your existing connection. DTEK Kyiv Regional Grids will issue technical conditions (TU) for the storage system. We handle the application and documentation.
Can I use a BESS as a backup during power cuts?
Yes, if the system is designed for island mode. But for industrial sites, we usually prioritize peak shaving and tariff optimization, because backup requires additional control and battery capacity.
What is the typical payback period for an industrial BESS?
In Kyiv Oblast with current tariffs, 5–7 years is realistic, assuming two-zone tariff and a peak load that lasts 1–2 hours. The exact figure depends on your load profile and the difference between day and night rates.
What maintenance does a BESS require?
Minimal: visual inspections, cleaning the cooling filters, and checking the BMS data remotely. We offer a service contract for 24/7 monitoring and preventive maintenance every 6 months.

Figures shown are indicative. Exact sizing follows a site survey and load-profile analysis.